Follow your application through the approval process.
Once all departments have completed their initial reviews, the permit specialists will prepare a single information request report containing all comments from all departments.
Do not email revised documents!
You will be allowed to upload revised documents when the current round of reviews is complete, and the information request report is created.
| Step |
Status |
Date |
| ROW Final Inspect w/ Bond Rel
(view notes) |
Completed |
12/4/2009 |
| Right of Way Permit Extension
(view notes) |
Completed |
3/12/2008 |
| Right of Way Permit Issuance
(view notes) |
Completed |
1/8/2008 |
| Application Received
(view notes) |
Completed |
11/13/2007 |
| Right of Way Permit Extension
(view notes) |
Completed |
4/11/2008 |
| Right of Way Review
(view notes) |
Completed |
11/12/2008 |