PLN51880A CUP Conditional Use Permit
Address:
NE Baker Hill Rd
Bainbridge Island,  WA  98110
Parcel #: 04240210542005
Status: Approved and closed
Submitted: 2/23/2021
Approved: 6/23/2021
Issued: 6/23/2021
Closed: 7/21/2021
Expires: 12/20/2021
Inspections:
Required: 1
Complete: 1
Total Fees:
$10,49400
Additional fees may be required
Project: AT&T proposes to install an unmanned telecommunications facility on the 35'7" KPUD #1 Water Tower. Proposal includes the attachment of 12 antennas, 18 remote radio units, 2 surge protectors & fiber/DC cables; Ground equipment includes a 6'8" x 6'8" Walk-in Cabinet (WIC) on a 20' x 6' concrete pad within the existing KPUD facility.

Public Notice
Description Begin Date End Date
Notice of Application and Hearing 4/2/2021  
Hearing Examiner Decision 06232021 6/24/2021  

Contacts
:
PUBLIC UTILITY DIST NO 1 OF KITSAP COUNTY
:
Smartlink LLC

Contractors

Details

Parcels
Parcel(s) associated with your permit.
Parcel Owner Address
04240210542005 PUBLIC UTILITY DIST NO 1 OF KITSAP COUNTY **NO SITUS ADDRESS **
UNKNOWN,  WA 00000

Submittals
If any submittal item(s) listed below is noted as "required", you will not be able to issue your permit. Please upload the required submittal item before proceeding.
Submittal Required Received Accepted
REVISION 2 Yes 6/9/2021 6/9/2021
REVISION 1 Yes 4/12/2021 7/21/2021
Title Report Yes 2/23/2021 3/24/2021
Stormwater Pollution Prevention Plan (SWPPP) Drawings Yes 2/23/2021 3/24/2021
Miscellaneous Documents Yes 2/23/2021 3/24/2021
Plan Set Yes 2/23/2021 3/24/2021
Elevation Plan (view notes) Yes 2/23/2021 3/24/2021
Outdoor Lighting Plan (view notes) Yes 4/15/2021 4/15/2021
Decision Criteria (view notes) Yes 2/23/2021 3/24/2021
Design Guideline Checklist Yes 2/23/2021 3/24/2021
Traffic Impact Analysis (view notes) Yes 3/24/2021 3/24/2021
Landscape Plan Yes 2/23/2021 3/24/2021
Tree Retention Plan (view notes) Yes 3/24/2021 3/24/2021
Vicinity Map (view notes) Yes 3/24/2021 3/24/2021
Owner Agent Agreement (view notes) Yes 2/23/2021 3/24/2021
Utility Plan Yes 7/21/2021 7/21/2021
Project Narrative Yes 3/24/2021 3/24/2021
Pre-Application Letter (view notes) Yes 3/24/2021 3/24/2021
Kitsap Public Health District Documentation (view notes) Yes 7/21/2021 7/21/2021
Project Application Yes 2/23/2021 3/24/2021
Site Plan Yes 2/23/2021 3/24/2021

Approval Steps
Follow your application through the approval process.
Step Status Date
Completeness Review (view notes) Application deemed complete 3/24/2021
Notice of Application Completed 3/25/2021
Posting of legal notices (view notes) Completed 4/7/2021
Application Complete Letter (view notes) Completed 3/24/2021
Application Incomplete Letter Completed 3/17/2021
Health District review Completed 5/17/2021
Operations & Maintenance Review Completed 4/23/2021
Planning Review Approved with Conditions 6/24/2021
Building Review (view notes) Approved 4/27/2021
Development Engineer Review (view notes) Approved with Conditions 4/23/2021
Fire Dept Review Approved 3/3/2021
Critical Area Review (view notes) Not Applicable 5/21/2021

Reviews
Start Complete Applicant Response
3/24/2021 6/24/2021

Fixtures
Fixture Quantity Per Unit Value
Total: $0.00

Valuations
Valuation Quantity Rate Value
Total: $0.00

Fees
Fee totals below may not reflect all fees, including fees calculated by hourly rates for resubmittals.
Fee Amount
Condition Use Permit Fee $10,494.00
Total : $10,494.00

Bonds
Type Number Amount Issued Expires Completed

Inspections
The inspections listed below are standard for all permits of this type. The inspections below may be inaccurate for a specific permit until that permit has been issued.
Completed On
Visit and document the site 4/19/2021

Structures
Structure Use Occupancy Type Square Footage

Conditions
The conditions listed below are standard for all permits of this type. The conditions below may be inaccurate for a specific permit until the permit has been issued.
Your portal access code is

Required Permits
Type Requirement For Number Status

Notes
Hearing Examiner Official Record 06/24/2021 - Uploaded to Laserfiche 6/24/2021
Email to commenter. 6/24/2021
Revised site plan received via email 6.9.2021 to reflect compliance with recommended condition of approval #5 that antennas are out of rear setback. 6/9/2021
HEX file- Exhibit packet. 6/3/2021
Recorded motion from 5/27/2021 Planning Commission Meeting 6/2/2021
Staff Report and Exhibits to Planning Commission 5/27/2021 5/21/2021
Health District Commercial Building Clearance approved, see attached. 5/17/2021
Planner info request with applicant response 5/12/2021
Email sent to commenters on previous application that was voided due to inactivity (PLN51880 CUP/WCF) 4/20/2021
Planner site visit 4.19.2021 4/19/2021
revised master land use application submitted - it omits the generator from the original scope of work. 4/12/2021
Proposed Timeline & updated proposed timeline 3/25/2021
Response to Notice of Incomplete Application received via email from applicant on 3.22.2021 3/22/2021
updated Owner Agent Agreement 3/12/2021
Submitted documents 2/23/2021

Associations