Contact
BLD21580 Residential Alteration
Address:
611 Fairview Ave NE
Bainbridge Island,  WA  98110
Parcel #: 41130010040000
Status: Permit has been issued to applicant.
Submitted: 6/3/2016
Approved: 8/26/2016
Issued: 9/8/2016
Closed:
Expires: 2/24/2018
Inspections:
Required: 12
Complete: 7
Total Fees:
$2,77694
Additional fees may be required
Project: Major Remodel of SFR. See Attached List. New attic insulation, crawl space insulation, conver to zero clearance LP fireplaces, install 500 gallon Underground LP Tank.

Public Notice

Contacts
OWNER: CITRON MICHAEL & LYN LIVING TRUST
APPLICANT: CITRON MICHAEL & LYN LIVING TRUST

Contractors

Details

Parcels
Parcel Owner Address
41130010040000 CITRON MICHAEL & LYN LIVING TRUST 611 Fairview Ave NE
Bainbridge Island,  WA 98110

Submittals
If any submittal item(s) listed below is noted as "required", you will not be able to issue your permit. Please upload the required submittal item before proceeding.
Submittal Required Received Accepted
Project application Yes 6/3/2016 n/a
Site Plan Yes 6/3/2016 n/a
Kitsap Public Health District Documentation Yes
Completed Energy Code Worksheet Yes 6/3/2016 n/a
Plans - 2 sets of building plans Yes 6/3/2016 n/a
Engineered construction plans and calculations Yes 6/3/2016 n/a

Approval Steps
Step Status Date
Planning Review Completed 6/3/2016
Building Review Approved 8/4/2016
Fire Dept Review Approved with Conditions 6/14/2016
Health District-  BSA/BC Not Applicable 8/26/2016

Reviews
Start Complete Applicant Response
6/3/2016 8/26/2016

Fixtures
Fixture Quantity Per Unit Value
Total: $0.00

Valuations
Valuation Quantity Rate Value
Entered Valuation 125000.00 $1.00  / DOLLAR $125,000.00
Total: $125,000.00

Fees
Fee totals below may not reflect all fees, including fees calculated by hourly rates for resubmittals.
Fee Amount
Planning Review Fee $226.75
Plan Check Fee $736.94
Fire Protection Review $300.00
Building Permit Fee $1,133.75
SBCC $4.50
Water Connection $225.00
Water Availability Request $50.00
Water Connection Inspection $100.00
Total : $2,776.94

Bonds
Type Number Amount Issued Expires Completed

Inspections
The inspections listed below are standard for all permits of this type. The inspections below may be inaccurate for a specific permit until that permit has been issued.
Completed On
Exterior Shear Wall Nailing Inspection 9/22/2016
Interior Shearwall Inspection 10/11/2016
Mechanical, Rough-In Inspection 9/1/2017
Plumbing, Rough-In Inspection 9/1/2017
Framing Inspection 9/1/2017
Caulk and Seal Inspection 9/1/2017
Insulation Inspection 9/14/2017
Gypsum Wallboard Inspection
Fire Department Final Inspection (Call 206-451-2033)
Final Building Inspection
Cross Connection Control (Call Public Works)
Side Water Connection Inspection (Call Public Works)

Structures
Structure Use Occupancy Type Square Footage
Major Remodel of SFR. See Attached List. New attic insulation, crawl space insulation, conver to zero clearance LP fireplaces, install 500 gallon Underground LP Tank. SFR

Conditions
The conditions listed below are standard for all permits of this type. The conditions below may be inaccurate for a specific permit until the permit has been issued.
Approved plans shall not be changed, modified or altered without authorization from the Building Department. Revisions shall be submitted and approved by the Department of Planning and Community Development prior to inspection.
Any equipment and/or appurtenances not shown on this approved site plan (i.e. mechanical equipment, retaining walls, decks, etc.) are not approved. Revisions to plans must be submitted to COBI for approval prior to installation.
Structures designed with shearwalls, holddowns and/or other designed attachment devices are subject to inspection prior to cover.
Permit Expiration: All permits expire 180 days after permit issuance, or 180 days after the last approved inspection activity is performed. The Building Official may extend the time for action for a period not exceeding 180 days, upon the receipt of a written extension request indicating that circumstances beyond the control of the permit holder have prevented action from being taken. Extension requests must be received prior to permit expiration, or additional fees will be due to reactivate the permit.
Building plans and review shall be subject to the 2012 International Codes, or subsequent edition as adopted by Bainbridge City Council at time of building permit application.
Any site retaining walls in excess of 4 feet in height will require a separate building permit under the City of Bainbridge Island Municipal Code Section 15.08.
ELECTRICAL WORK. If electrical work is proposed, a separate electrical permit is required. You can contact L&I at 360-415-4000 to obtain an electrical permit. Electrical systems must be inspected by L&I prior to requesting a framing inspection and final approval granted prior to requesting a final building inspection from the Department of Planning & Community Development.
Any grading in excess of 50 cubic yards will require a City of Bainbridge Island grading permit as identified in the 2012 IBC Section J 103.
Reinspection Fee: All approved construction plans, the approved site plan, the printed building permit, and the permit inspection placard are required to be on-site for inspection purposes, and work to be inspected shall be complete and ready for inspection. If an inspection is called for and plans are not available on site, or the work is not ready for inspection, or if previously identified corrections have not been made, approval will not be granted. In addition, a re-inspection fee will be charged and must be collected by the Department of Planning & Community Development prior to any further inspections being performed or approvals granted.
Final Inspection Required: All building permits shall have a final inspection performed and approved by the Department of Planning & Community Development prior to permit expiration. The failure to request a final inspection or failure to obtain final approval prior to expiration will be documented in the legal property records on file with Bainbridge Island as being non-compliant with Bainbridge Island ordinances and building regulations and will be referred to Code Compliance for action.
The project shall comply with the requirements of the adopted Fire Code and any applicable NFPA standards or other requirements as stipulated by the Fire Marshal.
A final inspection by the Fire Department is required. Please call 206-451-2033 to schedule your inspection. 48 hours notice is required for all Fire Department inspections.
Noise Regulations (Chapter 16.16). Construction activities (site preparation, assembly, construction, erection, demolition, substantial repair, alteration or similar action on a property, buildings, structures or activities) within residential zones or within 100 feet of residential zones shall (A) be prohibited between the hours of 7:00pm and 7:00am on weekdays that do not constitute legal holidays; (B) be prohibited before 9:00am and after 6:00pm on Saturdays that do not constitute legal holidays; (C) be prohibited on Sundays and all legal holidays except that work on the inside of an enclosed structure may occur between the hours of 10:00am and 4:00pm.
State Legal Holidays for 2016: January 1, January 18, February 15, May 30, July 4, September 5, November 11, November 24, November 25, December 23 & December 26.
Any new smoke alarm/carbon monoxide alarms shall be interconnected to existing alarms.
Bedrooms with fuel burning fireplaces shall be equipped with a carbon monoxide detector.

Required Permits
Type Requirement For Number Status

Notes

Associations