Contact
PLN51157 SSDP Shoreline Substantial Development Permit
Address:
6150 NE EAGLE HARBOR DR
BAINBRIDGE ISLAND,  WA  98110
Parcel #: 34250210082005
Status: Application has all components for review.
Submitted: 8/15/2018
Approved:
Issued:
Closed:
Expires: 2/17/2019
Inspections:
Required: 4
Complete: 0
Total Fees:
$2,28967
Additional fees may be required
Project: Construct new single-family recreational pier, ramp, float, boat lift and mooring buoy. Remove the 80 foot concrete bulkhead (for mitigation)and replace 50% on the west side with a soldier pile and concrete slab bulkhead. Replace 50% on the east side with a pocket beach, supported by landscape rock, root wads, native vegetation and stone steps.

Contacts
OWNER: LAPINSKI JOHN S & SHAW LAPINSKI ANJALI V
APPLICANT: LAPINSKI JOHN S & SHAW LAPINSKI ANJALI V
AGENT: SHORELINE SOLUTIONS LLC

Contractors

Details

Parcels
Parcel Owner Address
34250210082005 LAPINSKI JOHN S & SHAW LAPINSKI ANJALI V 6150 NE EAGLE HARBOR DR
BAINBRIDGE ISLAND,  WA 98110

Submittals
If any submittal item(s) listed below is noted as "required", you will not be able to issue your permit. Please upload the required submittal item before proceeding.
Submittal Required Received Accepted
Shoreline, wetland or stream habitat report, where applicable Yes 8/15/2018 8/15/2018
Plan set Yes 8/15/2018 8/15/2018
Geotechnical Report Yes 8/15/2018 8/15/2018
Site Photos Yes 8/15/2018 8/15/2018
Owner/Agent Agreement Yes 8/15/2018 8/15/2018
Decision Criteria Yes 8/15/2018 8/15/2018
Pre-Application Letter Yes 8/15/2018 8/15/2018
No net loss report - Ecological Functions and Processes Yes 8/15/2018 8/15/2018
Project application Yes 8/15/2018 8/15/2018
Site Plan Yes 8/15/2018 8/15/2018
Environmental (SEPA) Checklist Yes 8/15/2018 8/15/2018

Approval Steps
Step Status Date
Completeness Review In Process 8/15/2018
Notice of Application Pending 8/15/2018
Application Complete Letter Completed 9/12/2018
Application Incomplete Letter Not Applicable 9/12/2018
FEMA Flood Review In Process 8/15/2018
Planning Review In Process 8/15/2018
Development Engineer Review In Process 8/15/2018
Department of Fish & Wildlife In Process 8/15/2018
RAA Application Review In Process 8/15/2018
Critical Area Review In Process 8/15/2018

Reviews
Start Complete Applicant Response
8/21/2018

Fixtures
Fixture Quantity Per Unit Value
Total: $0.00

Valuations
Valuation Quantity Rate Value
Total: $0.00

Fees
Fee totals below may not reflect all fees, including fees calculated by hourly rates for resubmittals.
Fee Amount
Shoreline Substantial Development Permit $2,289.67
Total : $2,289.67

Bonds
Type Number Amount Issued Expires Completed

Inspections
The inspections listed below are standard for all permits of this type. The inspections below may be inaccurate for a specific permit until that permit has been issued.
Completed On
Visit and document the site
Temporary Construction Access
After rough grading is complete (Call Public Works 206-780-3739)
Road Approach - Final (Call Public Works 206-780-3739)

Structures
Structure Use Occupancy Type Square Footage

Conditions
The conditions listed below are standard for all permits of this type. The conditions below may be inaccurate for a specific permit until the permit has been issued.

Required Permits
Type Requirement For Number Status

Notes
Chad Croker to install buoy. 8/15/2018
SEPA Checklist staff reviewed version 10/8/2018
Notice Mailing List 101218. Notice of Affidavit & Invoice. 10/10/2018
REVISED Site Plan received 10/30/18 11/2/2018
Public Comment attached 11/14/2018
Applicant response to public comments 11/26/2018