PLN50958 SPR Site Plan Review
Address:
Madison Ave S
Bainbridge Island,  WA  98110
Parcel #: 26250230782006
Status: Application has all components for review.
Submitted: 2/28/2018
Approved:
Issued:
Closed:
Expired: 10/20/2018
Inspections:
Required: 1
Complete: 0
Total Fees:
$11,08600
Additional fees may be required
Project: Development of courtyard style 10 unit residential building with under building parking.

Contacts
OWNER: CKCB MADISON AVENUE DEVELOPMENT LLC
APPLICANT: CKCB MADISON AVENUE DEVELOPMENT LLC

Contractors

Details

Parcels
Parcel Owner Address
26250230782006 CKCB MADISON AVENUE DEVELOPMENT LLC **NO SITUS ADDRESS **
UNKNOWN,  WA 00000

Submittals
If any submittal item(s) listed below is noted as "required", you will not be able to issue your permit. Please upload the required submittal item before proceeding.
Submittal Required Received Accepted
Project Narrative No 2/28/2018 4/23/2018
Shoreline, wetland or stream habitat report, where applicable No 2/28/2018 4/23/2018
Geotechnical Report No 2/28/2018 4/23/2018
Plan set No 2/28/2018 4/23/2018
Decision Criteria Yes 2/28/2018 4/23/2018
Design Guideline Checklist Yes 2/28/2018 4/23/2018
Traffic impact analysis Yes 11/14/2018 11/14/2018
Pre-Application Letter Yes 2/28/2018 4/23/2018
Water Availability letter Yes
Sewer availability letter Yes
Community Meeting Summary Yes 2/28/2018 4/23/2018
Environmental (SEPA) Checklist Yes 2/28/2018 4/23/2018
Project application Yes 2/28/2018 4/23/2018
Submitted Associated Plans and Details No 4/23/2018 4/23/2018
Building Elevations - Exterior views of building(s) No 4/23/2018 4/23/2018

Approval Steps
Step Status Date
Completeness Review Application deemed complete 4/23/2018
Application Complete Letter Completed 4/23/2018
Traffic Study/Analysis Review Approved 11/21/2018
Geotechnical Review by 3rd Party Approved 1/17/2019
Planning Commission Review Completed 1/30/2019
Health District review Not Applicable 4/23/2018
Operations & Maintenance Review Completed 5/11/2018
Planning Review In Process 2/27/2018
Fire Dept Review Completed 3/19/2018
Development Engineer Review Approved with Conditions 1/30/2019
Design Review Board Completed 4/23/2018
Non-Motorized Transportation Commission Approved 6/13/2018
Building Official Review Approved 1/18/2019

Reviews
Start Complete Applicant Response

Fixtures
Fixture Quantity Per Unit Value
Total: $0.00

Valuations
Valuation Quantity Rate Value
Total: $0.00

Fees
Fee totals below may not reflect all fees, including fees calculated by hourly rates for resubmittals.
Fee Amount
Site Plan Review $8,586.00
Geologically Hazardous Area Third-Party Geotechnical Review Fee $2,500.00
Total : $11,086.00

Bonds
Type Number Amount Issued Expires Completed

Inspections
The inspections listed below are standard for all permits of this type. The inspections below may be inaccurate for a specific permit until that permit has been issued.
Completed On
Road Approach Inspection

Structures
Structure Use Occupancy Type Square Footage

Conditions
The conditions listed below are standard for all permits of this type. The conditions below may be inaccurate for a specific permit until the permit has been issued.
Your portal access code is

Required Permits
Type Requirement For Number Status
Water/Sewer Availability No PW18 0029 Closed

Notes
Notice of Application w/SEPA. Memo. Mailing List. Notice Invoice. 4/3/2018
Public Comment attached 4/5/2018
Legal Notice Memo Revised Legal Notice Revised Mailing List Certificate of Posting. Notice Invoice. 6/6/2018
MTAC Comments 8/3/2018
Mailing List 010819. Notice Postcard. Notice Invoice/Affidavit of Posting. 1/10/2019
Certificate of Posting 1/16/2019
Planning Commission Materials 1/18/2019
Public Comment attached 1/20/2019
Hearing Examiner Exhibits 2/7/2019
3rd Party Geotechnical Review Invoice #047704 - $1,622.95 3/5/2019

Associations