Contact
PLN15063 SSDP Shoreline Substantial Development Permit
Address:
10016 NE EWING ST
BAINBRIDGE ISLAND,  WA  98110
Parcel #: 35250220952006
Status: Completeness Review in process
Submitted: 10/10/2017
Approved:
Issued:
Closed:
Expires: 4/8/2018
Inspections:
Required: 1
Complete: 0
Total Fees:
$6,86900
Additional fees may be required
Project: Construct new single use 280' long pier/ramp/float/boatlift/stairway in Eagle Harbor.

Public Notice

Contacts
APPLICANT: CAMPBELL MARK J & STACI M
OWNER: CAMPBELL MARK J & STACI M
AGENT: SHORELINE SOLUTIONS LLC

Contractors

Details

Parcels
Parcel Owner Address
35250220952006 CAMPBELL MARK J & STACI M 10016 NE EWING ST
BAINBRIDGE ISLAND,  WA 98110

Submittals
If any submittal item(s) listed below is noted as "required", you will not be able to issue your permit. Please upload the required submittal item before proceeding.
Submittal Required Received Accepted
Resubmittal 1 No 11/17/2017 n/a
SAR Application No 10/10/2017 n/a
Survey of Property No 10/10/2017 n/a
Marine Report No 10/10/2017 n/a
Geotechnical Report No 10/10/2017 n/a
Site Photos No 10/10/2017 n/a
Owner/Agent Agreement Yes 10/10/2017
Map Yes 10/10/2017
Pre-Application Letter Yes 10/10/2017
No net loss report - Ecological Functions and Processes Yes 10/10/2017
Project application Yes 10/10/2017
Cross Section Plans Yes 10/10/2017
Site Plan Yes 10/10/2017
Environmental (SEPA) Checklist Yes 10/10/2017

Approval Steps
Step Status Date
Completeness Review Application deemed complete 12/8/2017
Notice of Application Pending 10/10/2017
Application Complete Letter Completed 12/8/2017
Application Incomplete Letter Completed 11/8/2017
FEMA Flood Review In Process 10/10/2017
Planning Review In Process 12/1/2017
Development Engineer Review In Process 10/10/2017
Department of Fish & Wildlife In Process 10/10/2017

Reviews
Start Complete Applicant Response

Fixtures
Fixture Quantity Per Unit Value
Total: $0.00

Valuations
Valuation Quantity Rate Value
Total: $0.00

Fees
Fee totals below may not reflect all fees, including fees calculated by hourly rates for resubmittals.
Fee Amount
Shoreline Substantial Development Permit $6,869.00
Total : $6,869.00

Bonds
Type Number Amount Issued Expires Completed

Inspections
The inspections listed below are standard for all permits of this type. The inspections below may be inaccurate for a specific permit until that permit has been issued.
Completed On
Visit and document the site

Structures
Structure Use Occupancy Type Square Footage

Conditions
The conditions listed below are standard for all permits of this type. The conditions below may be inaccurate for a specific permit until the permit has been issued.

Required Permits
Type Requirement For Number Status

Notes
Notice of Application. Memo. Mailing List. Notice Invoice. Certificate of Posting. 12/12/2017
Correspondence with ECY 12/18/2017

Associations