PLN51836 SUB Preliminary Subdivision
Address:
1332 WINTERGREEN LN NE
BAINBRIDGE ISLAND,  WA  98110
Parcel #: 23250230942009
Status: Application received and pending acceptance
Submitted: 2/10/2021
Approved:
Issued:
Closed:
Expires:
Inspections:
Required: 3
Complete: 0
Total Fees:
$100,94800
Additional fees may be required
Project: Revised to 73 lot subdivision. The Wintergreen 74 townhome project is proposed for two lots with 2.93 acres of land area. Adding the 74 townhomes to the Wintergreen Center that has Key Bank, Walgreens, and Virginia Mason will create a "Mixed Use" Center. The project also meets BIMC affordable home requirements.

Public Notice
Description Begin Date End Date
Notice of Application/SEPA Comment Period/Hearing 043021 4/29/2021  
Notice of Public Hearing 11/19/2021  

Contacts
:
VWA-BI-LOTS LLC
:
CENTRAL HIGHLANDS INC

Contractors

Details

Parcels
Parcel(s) associated with your permit.
Parcel Owner Address
23250230942009 VWA-BI-LOTS LLC 1332 WINTERGREEN LN NE
BAINBRIDGE ISLAND,  WA 98110
23250230922001 VWA-BI-LOTS LLC 1329 WINTERGREEN LN NE
BAINBRIDGE ISLAND,  WA 98110

Submittals
If any submittal item(s) listed below is noted as "required", you will not be able to issue your permit. Please upload the required submittal item before proceeding.
Submittal Required Received Accepted
REVISION 5 Yes 6/15/2021
REVISION 4 Yes 6/11/2021
REVISION 3 Yes 4/21/2021
REVISION 2 Yes 4/12/2021 4/15/2021
REVISION 1 (view notes) Yes 3/29/2021 4/15/2021
Miscellaneous Documents Yes 2/26/2021 4/15/2021
Preliminary Subdivision Plan Yes 2/10/2021 4/15/2021
Water Availability Letter Yes 4/15/2021 4/15/2021
Sewer Availability Letter Yes 4/15/2021 4/15/2021
Title Report Yes 3/1/2021 4/15/2021
Tree Retention Plan Yes 3/8/2021 4/15/2021
Traffic Impact Analysis Yes 2/10/2021 4/15/2021
Stormwater Management (SWM) Plan Yes 2/10/2021 4/15/2021
Conditions Covenants and Agreements (Existing and Proposed Terms) Yes 2/10/2021 4/15/2021
Vicinity Map Yes 2/10/2021 4/15/2021
Owner Agent Agreement Yes 3/29/2021 4/15/2021
Preliminary Open Space Management Plan (view notes) Yes 2/10/2021 4/15/2021
Project Narrative Yes 2/10/2021 4/15/2021
SEPA Environmental Checklist Yes 2/10/2021 4/15/2021
Pre-Application Letter Yes 2/10/2021 4/15/2021
Project Application Yes 2/10/2021 4/15/2021
Site Plan Yes 2/10/2021 4/15/2021

Approval Steps
Follow your application through the approval process.
Step Status Date
Completeness Review (view notes) Application deemed complete 4/15/2021
Notice of Application Completed 4/30/2021
Posting of legal notices (view notes) Completed 4/30/2021
Application Complete Letter (view notes) Completed 4/15/2021
Application Incomplete Letter (view notes) Completed 3/9/2021
Survey Review In Process 2/26/2021
Health District review Completed 9/28/2021
Planning Review In Process 2/26/2021
Fire Dept Review Approved 3/3/2021
Development Engineer Review Completed 10/25/2021
Operations & Maintenance Review Completed 8/26/2021
Non-Motorized Transportation Commission Not Applicable 8/26/2021
RAA Application Review Completed 8/26/2021
Critical Area Review (view notes) Approved 4/22/2021

Reviews
Start Complete Applicant Response
4/15/2021

Fixtures
Fixture Quantity Per Unit Value
Total: $0.00

Valuations
Valuation Quantity Rate Value
Total: $0.00

Fees
Fee totals below may not reflect all fees, including fees calculated by hourly rates for resubmittals.
Fee Amount
Long Subdivision (view notes) $102,093.00
Long Subdivision (view notes) -$1,145.00
Total : $100,948.00

Bonds
Type Number Amount Issued Expires Completed

Inspections
The inspections listed below are standard for all permits of this type. The inspections below may be inaccurate for a specific permit until that permit has been issued.
Completed On
Temporary Construction Access
After rough grading is complete (Contact Public Works: PWInspections@bainbridgewa.gov)
Road Approach - Final (Contact Public Works: PWInspections@bainbridgewa.gov)

Structures
Structure Use Occupancy Type Square Footage

Conditions
The conditions listed below are standard for all permits of this type. The conditions below may be inaccurate for a specific permit until the permit has been issued.

Required Permits
Type Requirement For Number Status

Notes
DRB Chair Dunstan comments to Planning Commission 8/31/2021
Revision # 7: Received 27AUG2021 8/27/2021
Staff-generated 2018 GIS aerial with 25' and 50' from SR305 right-of-way marked 8/30/2021
Public Comment attached 8/16/2021
REV 1 documents submitted 3-29-21 3/29/2021
Email note from H Gori and public comment 6/17/2021
REV 5: Documents submitted 6-15-21 6/15/2021
REV 4: Revision 6-11-21 SEE EMAIL FOR LINK TO VIDEO , REVISED RENDERINGS AND FLOOR PLANS 6/11/2021
Revised renderings submitted 5/21/2021
Notification to extend decision timeline 4/29/2021
SEPA checklist w/comments 4/30/2021
REV 3: Non-Binding Commitment for Water and Sewer System Capacity letter received 4-21-2021 4/21/2021
REV 2: Revised Documents submitted 4-12-2021 4/12/2021
Design for Bainbridge Worksheet - Design Review Board comments 3/16/2021
Tree Retention Plan and Tree Valuation received 3-8-2021 3/8/2021
Title Report info submitted 3-1-2021 3/1/2021
submitted documents 2/10/2021